- Broke ground and began footings for the West Parking Structure
- Completed Building 1, Level 1 elevated concrete deck
- Continuing construction of Building 1, Level 2 elevated concrete deck
- Mechanical, electrical, and plumbing contractors completing rough-ins behind concrete crews