Cormont Deer Valley® East Village

Construction Update

Q1 '26

  • Building 1 continues its upward progress, with the 4th floor concrete pour scheduled for the first week of April
  • Mechanical and plumbing rough-ins are underway on Level 0, keeping interior systems on pace with the rising structure
  • Building 5 Mat footings underway
  • West parking garage slab scheduled for early April, and plaza deck level lid completed before end of April.
  • Preparing site to begin East parking and Building 2 footings