Cormont Deer Valley® East Village
Construction Update
Q1 '26
- Building 1 continues its upward progress, with the 4th floor concrete pour scheduled for the first week of April
- Mechanical and plumbing rough-ins are underway on Level 0, keeping interior systems on pace with the rising structure
- Building 5 Mat footings underway
- West parking garage slab scheduled for early April, and plaza deck level lid completed before end of April.
- Preparing site to begin East parking and Building 2 footings