Cormont Deer Valley® East Village

Construction Update

October 2025

Below are the construction updates on the progress being made at Cormont at Deer Valley East Village for October 2025.

  • Tower 1: Underground mechanical, electrical and plumbing rough ins are ongoing.
  • All mat and perimeter footings are complete.
  • Level 1 concrete columns and walls are ongoing with first slab on grade pour scheduled for October.
  • Finalizing plaza landscaping design and Cormont amenity finishes.
  • West Parking garage and Tower 5 under permit review with Wasatch County.